Thursday, May 29, 2008

Schedule

My understanding of the timeline for the actual work:
6/2 (Mon) : Work starts -- demolition, framing
6/5 (Thu) : Cabinets delivered and installed (maybe just base ones)
Appliances need to be delivered
6/6 (Fri) : Counter template made and sink taken
6/7 (Sat) : Jon can hopefully rough out the plumbing
6/9 (Mon) : Upper cabinets, lighting, windows and door this week
6/10 (Tues) : Tile to be installed
6/11 (Weds) : Waiting for counter
6/16 (Mon) : Counter ready and installed
6/17 (Tues) : Plumbing can be installed
6/18 (Weds) : Inspections, painting
6/20 (Fri) : Job complete

I'm sure this will change frequently, but I need to record this now so I can compare it to the actual occurrences.

No comments: