Tomorrow David may be able to put in the window and finish the siding that was disturbed. The grout will be done, and I guess its up to me to paint this weekend. I will need to clean the surfaces first and then prime and paint.
Early next week the counters will be done, and I have the expectations of being ready to call Jon to do the plumbing for mid/late next week. I will get the appliances delivered for the following Monday, and I think we'll be 95% done at that point. Mike (the electrician) will need to come back and finalize the lights and plugs, along with the dishwasher and microwave.
I haven't spent any more in the last 2 weeks, or at least any more than I thought I would.