Also, it makes sense to add more recessed lights
to shine on the "work areas". Its actually going to
be pretty nice (top pic). There will be 5 or so of those spaced out to shine on the work areas, one fixture in the middle of the room for general light, and 2 recessed lights over the little peninsula (which I didn't think of before) to accentuate it (bottom pic). All of these will be on separate switches, and there will be switches for each area in 2 places (middle pic).
A couple of things they are fixing that we hated:
- There was no light switch at the kitchen entrance. It was by the back door. That will be fixed.
- The garbage disposal (aka "pig") will
have a switch up top instead of inside the sink cabinet.
- The stove plug will be where it belongs
- More plugs for appliances and stuff.
Jon came by and roughed out a couple plumbing-related things as well, so that tomorrow David can hang drywall, install the beam, and start prepping for cabinets. I appreciated him coming over on short notice.